Germany
Reuters | 6-Mar-2021
Vattenfall will get 1.606 billion euros and agreed to end pursuing a separate damages claim in the World Bank’s ICSID arbitration tribunal.
Le Soir | 5-Feb-2021
Le géant allemand de l’énergie RWE réclame à l’Etat néerlandais une compensation à son projet d’interdire la production d’électricité à l’aide de centrales au charbon. L’entreprise estime qu’elle pourrait subir 1,4 milliard d’euros de dommages.
CAN Europe | 4-Feb-2021
RWE has filed an arbitration claim against the Netherlands, seeking compensation for the Dutch decision to phase-out electricity production from coal by 2030.
DW | 12-Nov-2020
A lawsuit by Vattenfall is also still pending before the International Centre for Settlement of Investment Disputes (ICSID), concerning several billion euros for the permanent closure of Krümmel and Brunsbüttel.
Clean Energy Wire | 5-Oct-2020
The German government writes that around 21.7 million euros have been spent on lawyers, expert witnesses and court fees.
Le360 | 29-Jun-2020
Le 5 juin dernier, le président du tribunal du CIRDI a finalement reconnu la compétence de celui-ci pour juger l’affaire.
ARTE | 22-Apr-2020
À travers trois affaires significatives, un décryptage édifiant du pouvoir des tribunaux d’arbitrage internationaux, qui menacent de faire prévaloir les profits des multinationales sur l’intérêt général.
Medias24 | 6-Feb-2020
La procédure au fond suspendue dans le litige entre le Maroc et Sholz. La partie marocaine a soulevé une question de compétence. Sholz revoit ses prétentions à la baisse.
WirtschaftsWoche | 22-Jan-2020
The energy company Vattenfall is demanding compensation from the Federal Republic of Germany. The costs for the arbitration proceedings could exceed 20 million euros this year.